News


CATEGORY: Transport infrastructure, Urban Transport
LOCATION: Greece
START/END: 2008 - 2010
CLIENT: TERNA ENERGY S.A.
ORIGIN OF FUNDING: ATTIKO METRO
PARTNERS: ELBAS
PROJECT VALUE: 200.000
LDK’s BUDGET SHARE: 50%
STAFF PROVIDED: 5

Type of Services
- Traction Power Simulation and Stray Currents Study
- Traction Power Substations
- Traction power cables and Heat dissipation study
- Traction Current Removal (TCR) system
- General Release system
- Communications
- SCADA
Description
The project includes:
PERISTERI STATION
PERISTERI Station is constructed mainly using the C/C method along Panagi Tsaldari Av. where the town hall of Peristeri Municipality is located. Approximately thirty per cent (30%) of the Station is constructed using the underground boring method in order to mitigate any disturbance to normal traffic, since at this point there is a junction of six roads. PERISTERI Station will be composed of three levels with approximately the same outline (11,166 m2 total surface).
ANTHOUPOLI STATION
ANTHOUPOLI Station will be constructed using the C/C method underneath Anapafseos Street between Dodekanissou and Thivon Streets.
TWIN TRACK TUNNEL
1303m long, starting at FLEMING Shaft and terminating at West Blast Shaft.